Show/Hide Toolbars

CWT Compact S2 Installation & Maintenance Manual

Navigation: Installation > Site preparations

Placing the terminal on an existing concrete foundation

Scroll Prev Top Next More

The pedestal is attached directly to the foundation using 4–8 expansion bolts, see Figure below. The maximum bolt diameter is 12 mm.

The bottom plate extends 1.5 mm below the housing of the pedestal and you can place the pedestal directly on top of the foundation without any risk of damaging the housing.

Figure 30, Terminal placed directly on the foundation

Figure 30, Terminal placed directly on the foundation

 

Important:
Terminals for coin payment must be properly aligned vertically because the function of the anti-pin module and the coin verifier may be interrupted if the terminal leans more than a couple of degrees in any direction.